Construction of the New Terminal (No. 3) at Cairo International Airport.
The Project consists of:
-
343 linear meters of steel moulds which are used to execute 9,900 structural pre-cast beams.
- Pre-cast beams which are installed to form 5 floors of the Airport with a total area of 100,000 m2.
- 13 tower cranes, 5 mobile cranes and 2 gantry cranes which are used to produce and install pre-cast units.
|